Offshore wind
WPD has placed contracts for Baltic 1, Germany's first offshore wind farm in the Baltic Sea. Ballast Nedam,
a Dutch company, will be responsible for designing, delivering and
installing monopile foundations for 21 Nordex N90, 2.5 MW wind turbines.
The installation of the monopiles will start in January 2009 using the
Svanan floating crane, and A2SEA will begin installing the 21 turbines
in July 2009.
Iberdrola Renewables
has announced plans for 6 projects totalling 3 GW of capacity – off
Spain's Atlantic coast. The company has requested of the Ministry of
Industry that the offshore sites be reserved, so that it can conduct
studies prior to applying for permits to build the facilities at: Costa
de la Luz, Punta del Gato, Punta de las Salinas, Costa de Azahar, Costa
de la Luz and Banco de Trafalgar. Each site will have a capacity of 489
MW. Iberdrola's current project pipeline, excluding these projects,
stands at around 42 GW.
Construction is poised to restart at the
UK's Rhyl offshore wind farm. The Heavy Lifting Vessel (HLV) Svanen will
be installing the 25 foundations at the site, five miles off the north
Wales coast. HLV Svanen has worked around the world on major
construction projects. Its distinctive heavy lifting crane is capable of
hoisting an incredible 8500 tonnes, and stands over 80 m above the
water. Planning consent conditions allow the main offshore works to be
carried out between 1 April and 30 September, with certain activities
such as cable and wind turbine installation permitted up to mid
December.
Vestas
has scooped the contract to supply offshore wind turbines on the 330 MW
Belwind project on the Bligh Bank off Belgium. It will supply 110 V90
wind turbines. The award comes very soon after Vestas announced it would
be re-offering its problematic V90 to the market. The project, under
development by Dutch company Evelop, is located 46 km off Zeebrugge – in
20-35 m water depths – making it the furthest project yet built
offshore.
Construction on the project will begin this year, with
the 55, first phase offshore wind turbines being installed in 2009 for
operation in Q1 2010. The second phase of 55 wind turbines will be added
in 2010. All permits on the project have been received and financial
close is due mid-2008.
The UK's Gunfleet Sands II project has won approval. Under development by DONG,
the 64 MW offshore wind project is timetabled for completion in 2010,
and it is anticipated that it will chose the 3.6 MW Siemens wind
turbine. Gunfleet Sands I is due for completion in 2009.
Wave and Tidal
Marine Current Turbines
has successfully completed the first installation phase of the 1.2 MW
SeaGen Tidal System in Strangford Narrows, Northern Ireland (see image).
SeaGen
had its final assembly at the Harland & Wolff dockyard in Belfast.
The crane barge, Rambiz, owned by Scaldis, positioned the 1000 tonne
tidal power structure onto the seabed on 2 April. The quadropod section
that sits on the seabed will be pin piled. Each of the four pins that
secure SeaGen will be drilled to a depth of around 9 m. This work is
being carried out by Fugro Seacore Ltd.
SeaGen
is located 400 m from the shoreline. When fully operational, the tidal
turbine's16 m diameter, twin rotors will operate for up to 18–20 hours
per day.
SeaGen will enter commercial operation after a
commissioning phase of around 12 weeks and supply electricity to the
local grid. ESB Independent Energy – the retail subsidiary of ESB
(Ireland's national electricity company) – has signed a Power Purchase
Agreement with MCT to supply to its customers with the power produced by
SeaGen.
In other tidal news, Lunar Energy has sealed a joint venture agreement with the Korea Midland Power Company,
to develop a 300-turbine tidal power plant in the Wando Hoenggan
waterway off the South Korean coast. The project is timetabled for
completion in December 2015.
Last year, the company joined forces with E.ON UK,
to announce pioneering plans to develop a subsea tidal stream power
farm off the west coast of Britain by the end of 2009. The 8 MW UK pilot
plant will use 8 turbines up to 120 m below the surface.
The fabrication and installation of the Korean wind turbines will be carried out by Hyundai Heavy Industries, while Rotech Engineering will provide the specialist components.